Gujarat Metro Rail Corporation ( GMRC ) announces achievement of a new milestone
August 13, 2023
Gandhinagar: Gujarat Metro Rail Corporation (GMRC) in a note today stated that in endeavour to complete Ahmedabad Metro Rail Project Phase-II, from Motera to Mahatma Mandir and GNLU to Gift City by 2024, GMRC has achieved the milestone to erect composite girder at Ch-0 circle, Gandhinagar yesterday.
The salient features of composite girder erection are as follows: –
– The length between the supports is 47 meter where the girders are placed.
– The mass of the girders lifted and positioned is 300 MT
– The maximum weight that one crane can lift safely is 500 MT, we used two
cranes.
– Schedule for completion was 36 Hours, however, the operation was finished 12 hours earlier than scheduled time.
– This is the longest composite girder span in Ahmedabad Metro Rail Project Phase-II. The lifting was done in a restricted space without affecting the traffic flow at the crucial junction CH-0 circle with multiple shifting by cranes.
– After taking due permission of authorities, work executed on Highway with utmost safety and traffic management
-DeshGujarat
Recent Stories
- PM Modi proposes Thiru CP Radhakrishnan Ji's nomination for the Vice President
- India operates 24 nuclear power reactors with 8,180 MW capacity: Centre
- Closure of Tapi Bridge on Ahmedabad–Mumbai Highway Extended till Aug 20
- Pakistani Mohalla in Surat renamed to Hindustani Mohalla
- Multiple rounds of heavy rains likely in Saurashtra, Kutch, during 16-23 August: Weather analyst
- NHAI Rolls Out FASTag Annual Pass; List of Eligible Toll Plazas in Gujarat
- PM Modi announces Mission Sudarshan Chakra; aims to boost national security shield by 2035