Bhavnagar-Talaja-Mahuva road to be ready by June: Govt
February 09, 2023
New Delhi: The Bhavnagar-Talaja-Mahuva road project is being made in two parts and is anticipated to be completed by June 30, 2023, the Union Ministery of Road and Transport informed the Parliament.
In a response to Congress MP Shaktisinh Gohil, the ministry said “The Bhavnagar-Talaja-Mahuva (Gujarat) road project is being implemented under two packages i.e. Bhavnagar-Talaja (Package-1) and Talaja-Mahuva (Package-2).
The work of Bhavnagar-Talaja (Package-1) commenced on 07.02.2017 and the anticipated date of completion is 31.03.2023.
The work of Talaja-Mahuva (Package-2) commenced on 25.04.2017. However, the contract was terminated on 17.02.2021 due to the default of the Concessionaire. Now after the new contract has been awarded the anticipated date of completion is 30.06.2023.
The Ministry also mentioned the reason for the delay in the project, such as issues in land acquisition, Tautae Cylcone in May-2021, long monsoon durations and Termination and re-award of work on Package 2. DeshGujarat
Recent Stories
- PM Modi proposes Thiru CP Radhakrishnan Ji's nomination for the Vice President
- India operates 24 nuclear power reactors with 8,180 MW capacity: Centre
- Closure of Tapi Bridge on Ahmedabad–Mumbai Highway Extended till Aug 20
- Pakistani Mohalla in Surat renamed to Hindustani Mohalla
- Multiple rounds of heavy rains likely in Saurashtra, Kutch, during 16-23 August: Weather analyst
- NHAI Rolls Out FASTag Annual Pass; List of Eligible Toll Plazas in Gujarat
- PM Modi announces Mission Sudarshan Chakra; aims to boost national security shield by 2035